CORNER STAKESBat2

  For the sake of clarity, we'll call the first corner stake located on the baseline, point (A); and the second corner stake;( B). To find (C and D); refer to the site plans and note the exact depth of our structure; apply this figure by measuring from the corner stakes ( A and B ) the specified width or depth of the building, to points ( C and D ).This marks the rear structural line and is parallel with the baseline, set batter boards to this measurement using the same techniques described in setting the baseline batter boards. This set of batter-boards will hold the second line that we,re to put up to show the the exact width of our building site.  After you have this pair of batter boards installed; stretch the string and tie it to the 1X6 cross-members. Cut a slight groove in the top of the cross-member where the line intersects with the frame-work. These kerfs will hold the exact width of your building line. Do the same with the adjoining frame member.

Batter BoardsBat8

  Now; we have the base and rear line in place, it's good practice to make sure that the level of the batter boards is maintained throughout this process. With the transit set up in the center of your site, check and recheck the height and level of every installed batter board; the sides and the front and the two back boards and make adjustments if needed.

  Let's proceed with the last two batter boards which are built 8 or 10 feet beyond the back building line facing the two front batter boards. Easy!

BaselinesBit10

At a 90 degree angle to the baseline tie a string to the front batter board at corner stack (A) and pull it down the side of your structure to the opposite end and tie it to the back facing batter board. Check with a plumb-bob, the strings cross directly over corner stake (A). Then Check your angle by using a method based on the Pythagorean theorem and that is simply; from corner stake (A) measure 3 feet across one line (A,B) and 4 feet on the other line (A,C) mark these points, then measure across the two points which should equal 5 feet. This is called the 3,4,5 method.And you can obtain greater accuracy by increasing this number by two. For example 6,8,10 can be used. Lines have to be tight!

A quicker and easier way to square the corner is to set your transit directly over point (A)drop a plumb-bob centered directly over the stake. This will center your transit exactly over point (A). Set line (A,B) to 0 degree by pointing the transit at stake (B) and aligning the transit at 0 degree to stake (A). To find (C) turn the transit while maintaining the 0 degree mark pointing to stake (B) set the transit head to 90 degrees and sight down to the base board at point (C) and mark the transit cross hair location on top of the batter board, marking the spot for your line and where it should be tied to the batter board. Tie the string at the mark and re-check your 90 degree angle.Bat14

 With the angle verified and correct. Find point (D)by measuring the specified length indicated on the site plan point (C) to point (D),mark the location on the line, adjust your lines and tie it to the base board. Finally, check the diagonals of your site by measuring across the layout. Take a measurement from point (A,D) and compare that measurement to the diagonal of points (B,C)These lengths will be the same.

If everything went right with hardly no problems, your layout should be square. Go-to line intersection (A,C) drop a plumb-bob at this point and drive a 2X2 stake deep into the ground centered on the plumb-line, and place an 8 penny finish nail precisely at that spot. Do the same for the line intersection of point (B,D). And this completes the layout and the building line frame-work. Thank Goodness!!

  • Share/Bookmark

Related posts:

  1. Building: Site stakes & Foundation Prep
  2. Site: Grade, Layout & Building Stakes
  3. Survey Equipment
  4. Drainage/Footing Layout
  5. Setting The Forms

Related posts brought to you by Yet Another Related Posts Plugin.

Posted in Foundation, Framing, Layout, Preparation.

Tagged with , , , , , .


One Response

Stay in touch with the conversation, subscribe to the RSS feed for comments on this post.

  1. Karenac says

    Hey,

    I am regular visitor of this website.constructiontopic.com is filled with quality info. Let me tell you one thing guys, some time we really forget to pay attention towards our health. Let me show you one truth. Recent Research points that about 60% of all U.S. adults are either fat or weighty. Hence if you're one of these people, you're not alone. Infact many among us need to lose 10 to 20 lbs once in a while to get sexy and perfect six pack abs. Now next question is how you can achive quick weight loss? Quick weight loss can be achived with little effort. If you improve some of your daily diet habbits then, its like piece of cake to quickly lose weight.

    About me: I am blogger of Quick weight loss tips. I am also health trainer who can help you lose weight quickly. If you do not want to go under painful training program than you may also try Acai Berry or Colon Cleansing for quick weight loss.



Some HTML is OK

or, reply to this post via trackback.



Blog WebMastered by All in One Webmaster.
Easy AdSense by Unreal
Web Analytics Yellow Pages for USA and Canada

Search Engine Optimization and SEO Tools

Search Engine Optimization SEO

Performance Optimization WordPress Plugins by W3 EDGE
Blog WebMastered by All in One Webmaster.
Easy AdSense by Unreal
Web Analytics Yellow Pages for USA and Canada

Search Engine Optimization and SEO Tools

Search Engine Optimization SEO

Performance Optimization WordPress Plugins by W3 EDGE