Skip to content


Foundation Selection Criterion

 

More Points to Ponder

 

Settlement - The foundation must not settle to such an extent that it damages the structure. Settlement is deflection of the structure from its original setting. It is usually the result of movement or compaction of the underlying base soil and it may be due to construction on disturbed soil, backfill, and changes in the soil moisture content.

  Improper construction or design deficiencies in connection with other conditions may account for such foundation movement. Building on soil with voids, insufficient compaction, and loose fill will necessitate foundation movement or deflection. Many cases of settlement are caused by contractor error in over-excavating for the foundation and footers,and then incorrectly back-filling.

  Quality - The foundation must be of adequate quality so that it is not subjected to deterioration, such as a sulfate attack of concrete footings. Quality is an increasingly important concern in foundation construction. Cracks or other weaknesses in your foundation can cause many problems, and should be addressed immediately. Defects or failures in the constructed foundations can result in very large costs. Even with minor defects, remediation may be required.

  Adequate Strength - The foundation must be designed with sufficient strength that it does not fracture or break apart under the applied superstructure loads (live loads and dead loads). It must also be properly constructed in conformance with the design specifications.

  Adverse Soil Change - The foundation must be able to resist long-term adverse soil changes. An example is expansive soil ( silt and Clays ) which would expand and shrink causing movement of the foundation and damage to the structure.

  Seismic Forces- The foundation must be able to support the structure during an earthquake with out excessive settlement or lateral movement.

  The descision to use a particular foundation system that will be capable of meeting the specific requirements and specifications, will ultimately be guided by concerted efforts and contributions made by the departments of engineering, geo-tech engineers, and planning. These projected results are then factored into the structure that consequently determine the choice of footings.

  Some of those factors include but are not limited to the strength and compressibility of the soil ( characteristics of the soil ) on the site, estimated loads and distribution of said loads, transmitted throughout  the foundation, and the project performance criteria ( total settlement and differential settlement limitations ). So then the foundation design will be based on the assumed bearing capacity of the soil at the site.

  On construction sites where settlement is not a problem, shallow foundations are, for the most part, provide an economical foundation system and are typically utilized in many residential and light framed commercial structures.

In areas where poor soils are discovered, deep foundation systems may be employed to establish adequate bearing capacity and inhibit settlement.


Enjoy!           Have a good day!!

  • Share/Bookmark

Posted in Foundation, Uncategorized, footer, soil characteristics.

Tagged with , , , .


International and Uniform Code

STOP, BREAK, Hold Up!

   The International Residential Code (IRC) is a comprehensive, residential code that creates minimum regulations for one- and two-family dwellings of three stories or less. It also covers all building, plumbing, mechanical, fuel gas, energy and electrical provisions. The IRC also provides a prescriptive approach and a performance approach for determining compliance.

  At this point, before we get ahead of ourselves; I think its a good idea tolook at a few examples of the building codes pertaining to the information we've gleaned thus far. The codes concerning us at this point of the construction stage; where we touched on topics like, soil, grading, forms, foundations, and concrete slabs; we can see that there are specific references made for each of  these tasks that by the code are addressed and as such should be followed. Here, also; I want to look into general codes, basement and retaining walls, placement of steel, because these subjects will be part of the next building phases that we'll discuss in future post. You should familiarize yourself with these and many others, including local standards and amendments as well. The code specifications and requirements listed here touch on some of the pertinent points we've previously covered, and as we proceed I'll make reference to other specific building codes that certainly matter.

Before we leap into the trenches, lets see what these codes cover and the specific requirements needed to do the work right.

Soil, Grading and Drainage

The International Residential Code ( IRC ) and the Uniform Building Code ( UBC ) specification states that the grading from the foundation should be a minimum of 6 inches to every 10 feet within the first 10 feet from the foundation.   IRC [401.3]     UBC (1838.2). Keep in mind the exceptions to the rules are for example; in the case of local amendments or requirements (EXC).

Damp Proofed concrete and cement masonry units (CMU) foundations enclosing habitable or usable space require drainage, exception to the cited rule (EXC)..................03 IRC [405.1]       97 UBC (1834.1) 

Where underfloor area is on the same grade as exterior, alternative to the cited rule (OR)   IRC [405.1X]                UBC (1834.1X)

In well-drained ground or sand/gravel mixture...........IRC [405.1X]

Foundation minimum is 12 inches plus 2% above street drain........IRC  [403.1.7.3]              UBC (1806.5.5)

Foundation and slabs on expansive soils isolated from the expansive soil or designed to prevent damage.........IRC [403.1.8]            UBC (1804.4)

Forms

Lot slope greater than 1:10 foundation and footing stepped or level.....IRC [403.1.5]             UBC (1806.4)

Utility or other trench may not undermine the footing..........IRC [2604.4]             UBC (313.3)

Foundation sizing                  IRC [403.1.1]      UBC (1806.1)

One floor supported by foundation

  • Depth into previously undisturbed soil               12 inches
  • Wall thickness                                                                    6 inches
  • Footing thickness                                                             6 inches
  • Footing width                                                                   12 inches

Two floors supported by foundation

  • Depth into previously undisturbed soil          IRC [12 in.]  UBC (18 in.)
  • Wall thickness                                                                    8 inches
  • Footing thickness                                                             7 inches
  • Footing width                                                              IRC [12 in.]  UBC (15 in.)

Three floors supported by foundation

  • Depth into previously undisturbed soil          IRC [12 in.]   UBC ( 24 in.)
  • Wall thickness                                                            IRC [8 in.]     UBC (10 in.)
  • Footing thickness                                                              8 inches
  • Footing width                                                             IRC [17 in.]    UBC (18 in.)

Excavation fee of debris and roots       IRC [408.4, 506.2.1]   UBC (3302)

Pockets for untreated wood beams requirement 1/2 inch air space at ends and sides........................IRC [319.1]          UBC (2306.6) 

Basement and Retaining Walls

General

Damp-proofing required when enclosing habitable or usable space.......IRC [406.1]           UBC (1831)

Parge CMU walls prior to applying damp-proofing.........IRC [406-1]         UBC (1833.3)

Foundations retaining earth and enclosing usable space requirement footing drains discharging to approved drain system.........IRC [405.1]        UBC (1834.1)

No back-fill greater than 4 feet until walls anchored to floor............ICR [404.1.7]            UBC (1838.1)

When required reinforcement minimum distance from soil...........IRC [404.1.1.2]        UBC (n/a)

Minimum distance of vertical steel from soil side of wall

One floor supported by foundation

  • Thickness of wall                                                    8 inches
  • Distance face of soil to center fo steel           5 inches

Two floors supported by foundation

  • Thickness of wall                                                  10 inches
  • Distance face of soil to center of steel            6 .75 inches

Three floors supported by foundation

  • Thickness of wall                                                 12 inches
  • Distance face of soil to center of steel           8.75 inches

Basement requirements sump pumps exception group one soils........IRC [405.2.3]          UBC (1834.4)

Concrete Slabs

Concrete slabs

Slab floor on grade minimum 3.50 inches thickness........IRC [506.1]          UBC (1900.4.4)

Elevated or wood-supported slab requirements engineering...........IRC [2308.2]            UBC (2307)

Vapor retarder joints minimum 6 inch lap under habitable space..........IRC [506.2.3]                   UBC (1832.2)


P.S. I enjoy the comments and stay tuned for more to come. Have a good day!!

  • Share/Bookmark

Posted in Analysis, Codes, Planning, Preparation.

Tagged with , , , .




Blog WebMastered by All in One Webmaster.
Easy AdSense by Unreal
Web Analytics Yellow Pages for USA and Canada

Search Engine Optimization and SEO Tools

Search Engine Optimization SEO

Performance Optimization WordPress Plugins by W3 EDGE
Blog WebMastered by All in One Webmaster.
Easy AdSense by Unreal
Web Analytics Yellow Pages for USA and Canada

Search Engine Optimization and SEO Tools

Search Engine Optimization SEO

Performance Optimization WordPress Plugins by W3 EDGE